1 off 2000kVA 11kV Perkins powered generating set housed in an acoustic enclosure.
This generating set was provided to synchronise and load share with three existing
Broadcrown generators at this site.
The existing generators were located in the basement and were remotely cooled via air
blast coolers that are located in a well at roof level.
The problem facing Broadcrown was that there was no available space in the basement
for the installation of the 4th generator.
Following discussion between the contractor and Broadcrown Sales Department
it was agreed that the new generator could fit in the well where the existing air
blast coolers were located, at roof level of a 34 storey building.
Broadcrown undertook to remove the air blast coolers from the
well, re-install them directly on the roof of the building, re-connect them with temporary
pipework to the existing generators cooling system, re-test the existing generator to make
sure the movement of the coolers had no detrimental effect on existing generator operation.
This was done generator by generator as this was a live building and thus it was
imperative that the generator back up supply was available at all times.
Once the coolers had been moved to their temporary location, the new generator was positioned
in the light well. As the building was existing the only possible way to get equipment to roof
level was by a contractor-supplied tower crane installed on the roof of the building. The generator
and the acoustic enclosure had to be stripped down to within the 10,000kgs capability
of the crane. Lifting from the road side of the building was not possible, therefore the
generator components were lifted on to a barge and floated around the waterways to the opposite
side of the building and the crane lifted the components from the barge and onto roof level (34 storeys).
Following re-assembly of the generator in its acoustic enclosure, Broadcrown installed a steel gantry over the generator
enclosure, which had to be low height with side mounted exhaust system. Special attention was given to
air flows in and out of the generator enclosure because the gantry became the permanent location for the air blast coolers. These were then disconnected from their temporary position and re-installed on to the gantry and again this had to be
done without affecting the generator back up supply to the building.
When the re-located coolers were re-commissioned the new generator could then be commissioned with the three
existing generators.
Broadcrown's scope of supply also included the provision of a basement mounted fuel transfer system together with
approx 170 metres of feed and dump welded double-skinned pipework from the basement to the roof, together with changes
to the bulk tank installtion to incorporate the connection of the day tank for the additional generator.
|